![]() | ||||||
|
||||||
![]() |
|
||||||||||||||||||
Click HERE for a printable version of these documents
At one power plant where about 900,000 tons per year of coal is burned, Miltech assessed the amount of fly ash and scrubber sludge being generated, the cost involved and worked with the client to modify the sludge/fly ash recovery system involved. This sludge/fly ash system included:
In this system Miltech designed a centrifuge system, including the structure that housed the system. Miltech also oversaw the installation of the centrifuge recovery system.
Slaker Systems - Acid Mine Drainage Treatment In the treatment of acid mine drainage Miltech has been involved with systems that treat up to 15 million gallons of acid mine water per day. The most complex of these systems that have utilized Miltech services includes:
A key system within the overall AMD treatment process is the lime slaker system. For effective operation, the lime (calcium oxide) must be chemically converted to hydrated lime (calcium hydroxide) before it is used to treat the acid mine water. This process is called "slaking". The lime slaking system encompasses all of the equipment with associated controls starting from the lime feeder silo through the lime slaker slurry and lime grits removal. Miltech offers the following services related to design and maintenance of lime slaker systems in AMD processes:
For more information related to overall AMD treatment and sludge disposal see: Slaker Systems - Pollution Control in Coal Fired Power Plants Over the past several years Miltech has utilized its extensive experience with slaker systems in acid mine water treatment plants for the design, maintenance and modification of lime slaker systems in the pollution control processes of coal fired power plants. In these pollution control processes the slaked lime removes the SO2 from the gases by entering the scrubber with the scrubber water. At one power plant Miltech designed and supervised the modifications of three slakers in a 5-slaker system. These modifications also included:
System components included:
At this power plant operation Miltech was also involved in the re-design and modification of the scrubber sludge recovery and disposal system. For more information see Scrubber Sludge Recovery and Disposal.
Design calculations for the transportation of a slurry mixture from one location to another are similar to other pumping calculations, with additional considerations that must be included. The specific gravity of the slurry must be included in the calculation. A minimum slurry transportation velocity must normally be maintained to prevent the solid particles in the slurry from falling out of suspension. The abrasion characteristics of the slurry must be considered when evaluating pump wear components, and the abrasion resistance of the pipeline. Sometimes the temperature of the slurry affects the criteria for selecting pumps and piping, particularly if the slurry is pumped at an elevated temperature, as is sometimes the case with fly ash slurries. Miltech prepared slurry pumping evaluations, designs, and specifications for a power plant that planned to pump a fly ash slurry to a bore hole for injection into and abandoned underground coal mine. The total pumping distance was approximately 11,000' through a combination of 12" steel pipe and 16" thick-wall HDPE pipe. A booster pump was included in the system along the pipeline to prevent the pressure in the pipe from exceeding desired levels. The booster pump also allowed for the possibility of extending the pipeline to a more distant bore hole location in the future. The design had to take into account the critical settling velocity of the fly ash, the abrasive characteristics of the fly ash, the elevated temperature of the fly ash slurry, expansion and contraction issues, etc. Miltech provides slurry transportation services including the following:
For additional related information see:
In addition to designing and selecting the equipment for the aqua ammonia injection system, Miltech also assisted plant engineers and operators with selecting the location for the aqua ammonia storage tank, truck unloading station, pump skid and controls, and the flow meter panels. Once the aqua ammonia truck unloading and storage tank site was selected, Miltech prepared specifications for the demolition and removal of unused facilities at the selected location. Miltech then surveyed the site, prepared site grading plans, and prepared detailed designs for the installation of the concrete foundations and containments. Pipeline routing plans from the ammonia storage tank, to the pump skid, to the flow meter panels in the plant, and to the 12 ammonia injection lances were also prepared. A complete list of materials required for the project was provided to the client. For the particular project, Miltech provided on-site supervision and
inspection during site grading, and during installation of the concrete
foundations and containments. Miltech has the capability and expertise
necessary to follow through on all projects from the design phase, to the
construction and installation phase, and through the startup and initial
operation phases, as required by the client.
Miltech's volumetrics and density testing are done in accordance with ASTM procedures in order to ensure the maximum achievable accuracy.
Slurry is normally injected from the surface to underground mines via bore holes. Knowledge of underground mining and the ability to read mine maps are prerequisite to selecting the injection location. For old abandoned mines, relating underground locations to points on the surface can be tricky, if surface control points related to the underground mine coordinate system no longer exist. For such situations GPS technology sometimes proves to be useful. Surface ownership, environmental considerations, water supplies, and compliance with regulations all play roles in selecting a bore hole location, and in routing the pipeline to it. Miltech selected injection bore hole locations to an abandoned underground for a coal burning power plant desiring to inject fly ash into the mine. Miltech also designed the pumping and piping system from the power plant to the bore hole. For another client Miltech operates mine water treatment plants, and injects the sludge from those treatment plants back to the same mines. Miltech provides underground mine injection system design services including:
For additional related information see:
Click HERE for a printable version of these documents
|
||||
| The content of this internet site is the property of Miltech Energy Services, Inc., copyright © 2005 | ||